Mining News Pro - The New Mexico Environment Department announced via Twitter that it received word from the Environmental Protection Agency stating that the Gold King Mine wastewater treatment facility is back up and running following a failure reported on March 14, 2019, due to a loss of power.
According to Mining News Pro - The electric blackout was caused by a severe winter storm that struck the area this past week. The Gladstone plant, which is in charge of treating wastewater from the Gold King Mine in southwestern Colorado, was shut down.
The failure implied that wastewater from the mine started bypassing the facility at a rate between 250 to 300 gallons per minute. This is according to estimates from the neighbouring state of Utah and the U.S. Environmental Protection Agency.
The U.S. Geological Survey sent a sampling team to the area collect water and sediment samples at multiple points in New Mexico along the Animas and San Juan rivers, which were severely affected by the original leakage that took place back in 2015.
Nearby communities were also notified of the failure of the facility and were advised to take protective measures, such as shutting off intake points for drinking water systems.
The Gladstone plant was installed about three years ago after an EPA clean-up team working at the ancient mine accidentally caused the spill of over 3 million gallons of toxic wastewater. The effluent ran continuously for nine hours and ended up polluting the Animas River and its tributaries in New Mexico and Utah with the equivalent of four to seven days of ongoing acid drainage from the mine.
Short Link:
https://www.miningnews.ir/En/News/348042
South African diversified miner Sibanye Stillwater is discussing with lenders to temporarily lift limits on borrowings, ...
London-based Savannah Resources will if necessary ask Portugal’s government to authorize compulsory land acquisitions ...
Africa-focused Montage Gold announced Thursday it has received a ministerial order granting all environmental approvals ...
Newmont Corp. has no plans to expedite a decision on its $2.5 billion Yanacocha Sulfides project, dashing the Peruvian ...
Imports of iron ore by China, the world’s biggest buyer, in 2024 are expected to be around 1.17 to 1.18 billion metric ...
China’s central bank added 60,000 troy ounces of gold to its reserves in April, official data showed on Tuesday, ...
First Quantum Minerals said on Monday it is looking forward to talks with Panama’s new government to find a resolution ...
BHP has put South Africa and its mining sector on the spot. The $140 billion Australian group’s ambitious swoop on rival ...
Gold rose after mixed signals from the US, where optimism is growing the economy is on target for a soft landing as the ...
No comments have been posted yet ...