Mining News Pro - St Barbara will potentially increase the nameplate capacity at the Simberi gold operation in Papua New Guinea (PNG) by 10 per cent following the release of a feasibility study (FS) on the project.
The latest FS study updated the results of a pre-feasibility study in March 2020, pushing its plant nameplate capacity from 2.7 million tonnes per annum to three million tonnes per annum.
An option to expand to 3.7 million tonnes per annum was among other updates, as well as an improved all-in sustaining cost of about 3 per cent.
The board of St Barbara also approved a $US13 million ($16.7 million) pre-investment work, with a final investment decision targeted for March next year.
St Barabara managing director and chief executive Craig Jetson said the company was increasingly confident in the project.
“The future of the Simberi sulphide project has been endorsed by the board, with a commitment to pre-investment work that will take place as we update mineral reserves, complete reserve definition with drilling and finalise all pre-investment activities,” Jetson said.
“This vote of confidence in the Simberi operations comes as we work closely with the PNG government, agencies and community as part of our on-going consultation and engagement.”
St Barbara stated that the improved expectations in the sulphide mineralisation allowed for potential expenditure to increase.
This extra capital may include a power upgrade, closure costs and a full asset maintenance strategy.
Jetson detailed the full extent of the project’s updated prospects.
“Extensive marketing studies have allowed us to establish net smelter returns, while we’ve negotiated draft contracts giving us confidence in the concentrate market,” Jetson said.
“A new wharf will be constructed to enable 11,000 tonne concentrate shipments to Asian markets, which will result in significant cost savings.
“The fundamentals of this project are robust, with an anticipated mine life of around 11 years and a payback period of three years.”
St Barbara will now complete site trials for submission to the PNG Conservation & Environmental Protection Authority (CEPA).
Short Link:
https://www.miningnews.ir/En/News/613291
China’s Zhaojin Mining Industry said on Wednesday that its A$733 million ($477.8 million) offer to buy Australia’s ...
Toronto-listed miner OceanaGold Corp said on Wednesday it will raise 6.08 billion pesos ($106 million) through an ...
Gold’s record-setting rally this year has puzzled market watchers as bullion has roared higher despite headwinds that ...
AbraSilver Resource said on Monday it has received investments from both Kinross Gold and Central Puerto, Argentina’s ...
Gold took a tumble as haven demand waned after geopolitical tensions eased in the Middle East.
The four largest indigenous communities in Chile’s Atacama salt flat suspended dialogue with state-run copper giant ...
A prefeasibility study for Predictive Discovery’s (ASX: PDI) Bankan gold project in Guinea gives it a net present value ...
Representatives from the Peñas Negras Indigenous community, in northwestern Argentina, clashed with heavily armed police ...
Newmont confirmed on Wednesday that two members of its workforce died this week at the Cerro Negro mine located in the ...
No comments have been posted yet ...