Mining News Pro - Top copper producer Codelco is again delaying the return to normal operations at its Chuquicamata smelter.
According to Mining News Pro - Some parts of the smelter are operating normally, including the flash oven and one acid plant, a Codelco official said in an email in reply to questions from Bloomberg. A second acid plant will start ramping up within the next six days and the whole facility is expected to be up and running within the third quarter, the company said.
"The delay will likely result in another month of higher-than-normal concentrate shipments from Codelco."
Colin Hamilton, analyst at BMO CAPITAL MARKETS
In April, Codelco Chairman Juan Benavides said the plant would be fully operational by mid-year at the latest. The facility has remained shut for more than seven months, as Codelco failed to complete the works necessary to comply with tougher environmental standards that were implemented in December.
The facility is unlikely to return to normal capacity until mid-August, Rolando Milla, president of Chuquicamata Union No. 3 and union coordinator at the smelter, said in an interview Wednesday. The cancellation of Codelco’s contract with engineering firm SNC Lavalin Group Inc. forced the company to push back the timeline for the restart, he said.
‘All sorts of delays’
The smelter’s flash oven is now processing 70 to 80 tons of concentrate per hour, well below its normal capacity of 180 tons per hour, Milla said. Other parts of the plant aren’t fully operational, he said in an interview in nearby Calama.
“The use of contractor companies instead of Codelco’s own workers has resulted in all sorts of delays over the last few months,” Milla said. “We are asking our workers to get the smelter and the rest of the operations up and running as soon as possible – the company can’t blame us for these delays.”
A majority of Chuquicamata workers downed tools for two weeks last month amid a labor contract dispute with the company. Before the strike, Codelco had canceled its contract with SNC-Lavalin amid delays in the construction of two new acid plants at the smelter. Codelco took over the work after the contract was rescinded. Copper in London was little changed at $5,919 a ton on Thursday.
‘More stringent’
The delay will likely result in another month of higher-than-normal concentrate shipments from Codelco, Colin Hamilton, a BMO Capital Markets analyst, said in a research note on Thursday. “Given that environmental legislation in Chile is only becoming more stringent, we would not be surprised to see smelting facilities in the country close over time.”
The Chuquicamata mine was working at very limited capacity during last month’s strike, said Milla and Union No. 2 president Liliana Ugarte, contradicting an earlier company statement that it had been running at over 50% capacity.
During the strike, 14 trucks were operating at the mine’s pit — the world’s largest in size — compared with 70 to 80 trucks during normal times, Milla said. Workers are struggling to ramp up output to normal level as the two-week stoppage resulted in a backlog in some parts of the operation, Ugarte said in a separate interview in Calama on Wednesday.
Short Link:
https://www.miningnews.ir/En/News/393787
Oxford Economics Australia has released data showing mine maintenance spending may be hitting its peak. But what does it ...
Copper climbed above $10,000 a ton as predictions for tighter global supplies and rising consumption in electric ...
Canada’s mining industry is pushing for an carveout to the federal government’s proposed increase to capital gains ...
Copper output in Chile, the world’s largest producer of the metal, edged down in March, data from copper commission ...
Panama’s president-elect has ruled out talks with Canadian miner First Quantum Minerals until it drops multiple ...
Botswana President Mokgweetsi Masisi vowed to protect the country’s interests, including its 15% stake in diamond giant ...
Europe’s largest copper producer Aurubis AG reported first-half core profit above expectations on Wednesday, helped by ...
Copper briefly traded through $10,000 a ton as investors raised bets on Federal Reserve rate cuts, and Goldman Sachs ...
BHP’s plan to divest the South African assets of its target Anglo American are key to the strategy behind the proposed ...
No comments have been posted yet ...