Mining News Pro - WA Kaolin has started building works on the production plant at the Wickepin kaolin clay project in Western Australia.
AUSPAN has been contracted to complete the stage one building structural design and construction works and has mobilised at the site south of Perth.
The contractor’s team of 20 workers have started on the footings and laying the slab of the concrete batching plant, which was delivered to Wickepin on January 6.
WA Kaolin chief executive officer Andrew Sorensen said the company is on track to commence production plant building in February following the early works by AUSPAN.
AUSPAN general manager Ben Richardson added that mobilisation was underway and construction on site was ramping up following the Christmas break.
“Footings are almost complete, and we will be ramping up to a construction team of approximately 25 by early February,” Richardson said.
“With approximately 100 tonnes of structural steel already delivered to site, the landscape is about to change with the commencement of structural steel installation.”
These works are in line with WA Kaolin growing its kaolin contracts and orders with customers, with the Kwinana production facility is sold out on a two-shift five-day basis.
The Wickepin project is one of the largest known kaolin resources in the world, with an ore reserve estimate of 30.5 million tonnes to be mined over a 30-year mine life.
WA Kaolin has developed a dry processing method known as K99 to convert raw material into feedstock for global customers at a small-scale commercial processing plant at Kwinana.
The company, which already sells kaolin products from Wickepin for Tier 1 customers, is planning to boost production at Wickepin to 200,000 tonnes a year by the end of 2022.
Short Link:
https://www.miningnews.ir/En/News/610084
China’s Tianqi Lithium said on Thursday it has formally requested that a proposed joint venture between lithium company ...
Zimbabwe’s President Emmerson Mnangagwa has re-appointed Winston Chitando as the southern African nation’s mines ...
A new report by IDTechEx states that investing in e-haul trucks could result in major savings for miners due to the ...
Nigeria has revoked 924 dormant mining titles immediately and invites investors to freely apply for the affected ...
Copper traded near $10,000 a ton, hitting a new two-year high on its way, as investors continue to pile in on a bet that ...
Adriatic Metals is taking over as the operator of the Rupice deposit development, which is part of the company’s Vares ...
A prefeasibility study for Predictive Discovery’s (ASX: PDI) Bankan gold project in Guinea gives it a net present value ...
Iron ore futures prices drifted higher on Thursday as the latest soft data from top consumer China triggered renewed ...
Rio Tinto said on Wednesday it is teaming up with a global venture studio and start-up investor to back the development ...
No comments have been posted yet ...