Mining News Pro - A revised feasibility study into the Dolphin tungsten project, in Tasmania, has increased the project’s net present value by 65%, from A$146-million to A$241-million, with the addition of an underground operation.
King Island Scheelite on Wednesday also reported that the operational life of the project has been extended from 8 years to 14 years.
“The King Island Scheelite team has continued to successfully optimise and de-risk its 100% owned Dolphin tungsten project, both technically and commercially. As part of this process, we commissioned independent consultants to design an underground mine beyond the proposed opencut limits, estimate associated capital and operating costs, and revise the financial model to reflect the impact of the underground operation,” said chairperson Johann Jacobs.
“At the same time, we deemed it appropriate to also incorporate changes to the mineral processing flowsheet and operating parameters derived from recent metallurgical testwork.
“The significantly improved financial performance forecast bears testimony to our objective of optimising and de-risking the operation. Our key next steps are to secure an appropriate balance of debt and equity funding for the redevelopment of the Dolphin project,” Jacobs added.
A previously completed economic analysis of the Dolphin project estimated that some A$65-million would need to be invested to bring the opencut operation into production to produce 20 t/y of tungsten over an eight-year mine life.
The updated feasibility study has estimated a start-up capital cost of A$72.1-million to develop the Dolphin project, with life-of-mine capital estimated at A$129.2-million, placing capital cost for the operation at A$40/t of tungsten produced.
The project’s pre tax net present value has been estimated at A$241-million, with an internal rate of return of 43%, and a pay-back period of just over two years.
Average life of mine costs for the opencut operation has been estimated at A$126/t and for the underground operation at A$134/t.
Short Link:
https://www.miningnews.ir/En/News/609763
Mining News Pro - Tungsten cubes may have reached meme status as sales soar, yet that isn’t helping suppliers of the ...
Mining News Pro - Tungsten developer King Island Scheelite has entered into a new tungsten concentrate offtake agreement ...
Mining News Pro - The Northern Territory Government is expanding new exploration opportunities with 18 projects from 15 ...
Mining News Pro - A new report by Roskill states that the possible uptake of electric vehicles over internal combustion ...
Mining News Pro - The Australian Trade and Investment Commission (Austrade) has flagged strong demand for critical ...
Mining News Pro - King Island Scheelite has inked an offtake agreement with Kalon Resources to supply 1 500 t/y of ...
Mining News Pro - Premier African Minerals` RHA Tungsten project, in Zimbabwe, has received the go-ahead from the ...
Mining News Pro - The Northern Territory Government has awarded Thor Mining’s Molyhil tungsten and molybdenum project ...
Mining News Pro - Thor Mining made public an updated mineral resource estimate for its flagship Molyhil project in ...
No comments have been posted yet ...