Mining News Pro - An independent review has been completed on the feasibility study for the Egoli project at gold miner Pan African’s Evander mine, in Mpumalanga.
First gold is now expected to be produced about 20 months after construction starts, with ramp-up to steady state production to be achieved 16 months after that.
The low-cost brownfield project, which will capitalise on the Evander mine’s existing established infrastructure during its development and exploitation, has an initial life-of-mine (LoM) of nine years, with yearly gold production estimated at an average of 72 000 kg at an average head grade of 6.61 g/t.
Average LoM gold production is estimated at 17 771 kg, or about 570 000 oz.
Additional geological and operational upside exists when the inferred resources are accessed as underground development proceeds, which will potentially increase the LoM to 14 years.
In a report published on July 30, Pan African says the study “demonstrates a compelling organic growth project” with peak funding set at just over R1-billion with a capital payback period of 3.8 years from project inception.
All-in sustaining costs range at R399 600/kg, or $777/oz.
Detailed project scheduling and planning is in progress and is expected to be completed in the first quarter of 2021, while funding is expected to be finalised in the second quarter of 2021.
Inception of the Egoli project is scheduled to start in the second quarter of the 2021 financial year, with the dewatering of the decline followed by re-quipping, standard footwall development and further deepening of the decline and on-reef development.
The project also has a strong environmental social and governance credentials, as it is already fully licenced and empowered, the closure cost rehabilitation liability is fully funded and the company intends to utilise the existing tailings storage facility at Evander for the project, resulting in there being no additional environmental footprint.
The Evander solar plant, which will be completed in the next year, is expected to also contribute to cost savings and reduced emissions at Evander’s operations
Short Link:
https://www.miningnews.ir/En/News/575733
Barrick Gold faced criticism outside its annual general meeting on Tuesday in Toronto for supporting Malian rulers with ...
Gold wavered as traders looked ahead to a week with a Federal Reserve rate decision meeting and key US jobs data.
China’s Tianqi Lithium said on Thursday it has formally requested that a proposed joint venture between lithium company ...
Newmont Corp beat Wall Street estimates for first-quarter profit on Thursday, as the world’s largest gold miner ...
Zimbabwe’s President Emmerson Mnangagwa has re-appointed Winston Chitando as the southern African nation’s mines ...
China’s Zhaojin Mining Industry said on Wednesday that its A$733 million ($477.8 million) offer to buy Australia’s ...
Toronto-listed miner OceanaGold Corp said on Wednesday it will raise 6.08 billion pesos ($106 million) through an ...
A new report by IDTechEx states that investing in e-haul trucks could result in major savings for miners due to the ...
Nigeria has revoked 924 dormant mining titles immediately and invites investors to freely apply for the affected ...
No comments have been posted yet ...