Mining News Pro - A definitive feasibility study (DFS) into the Orokolo Bay industrial sands project, in Papua New Guinea, has estimated that the project would require a capital investment of $20.48-million.
Project owner Mayur Resources on Friday said that the DFS estimated that the project would generate revenues of some $969-million over a mine life of 15 years, producing 400 000 t/y of vanadium titano-magnetite, 100 000 t/y of magnetite for dense media separation, 8 000 t/y of zircon concentrate and 1-million tonnes a year of silica construction sand.
The study estimated that based on the five-million-tonne-a-year throughput rate, the Orokolo Bay project would have a post-tax net present value of $131-million and an internal rate of return of 103.7%, with life-of-project earnings before interest, taxes, depreciation and amortisation of $380-million.
“The results of the DFS are extremely encouraging and confirm the value of Mayur’s 51% interest in the Orokolo project of circa $67-million, which is roughly equivalent to the entire market value of Mayur Resources today,” said MD Paul Mulder.
“The market currently is effectively ascribing no value in the company’s other projects including our flagship Central and cement limestone project, which was recently awarded a mining lease and has a $352-million net present value, the Lae Energy Enviro Park, our coal assets or our copper and gold portfolio.”
Mulder said a mining lease application would be submitted for the Orokolo Bay project in October this year, with pilot plant construction and commissioning scheduled for the second quarter of 2021, depending on travel restrictions.
Commercial scale product trial shipments are targeted for the second quarter of 2021, and a final investment decision is being targeted for the second quarter.
Mayur earlier this week announced plans to spin out its Papua New Guinea gold and copper assets into a TSX-V listed entity, allowing the company greater focus and time to realise returns from the Orokolo Bay industrial sands project, and the Lae Enviro Energy Park and Central cement and lime project.
Short Link:
https://www.miningnews.ir/En/News/597981
The four largest indigenous communities in Chile’s Atacama salt flat suspended dialogue with state-run copper giant ...
A prefeasibility study for Predictive Discovery’s (ASX: PDI) Bankan gold project in Guinea gives it a net present value ...
A Native American group has asked all members of a US appeals court on Monday to overturn an earlier ruling that granted ...
Codelco is exploring more partnerships with the private sector as Chile’s state copper behemoth looks to recover from a ...
Representatives from the Peñas Negras Indigenous community, in northwestern Argentina, clashed with heavily armed police ...
The London Metal Exchange (LME) on Saturday banned from its system Russian metal produced on or after April 13 to comply ...
Peru’s Las Bambas copper mine, owned by China’s MMG, is facing renewed blockades of a key transport route after failed ...
Vitol Group confirmed that it’s starting to rebuild a trading book for metals after a long stint out of the market, with ...
Newmont confirmed on Wednesday that two members of its workforce died this week at the Cerro Negro mine located in the ...
No comments have been posted yet ...