Mining News Pro - Rio Tinto is challenging the findings of an independent review into $1.4 billion in cost overruns and delays at the Oyu Tolgoi mine in Mongolia, restating the project’s troubles were caused by unpredictable geology issues.
The Independent Consulting Group’s (IGG) report concluded last month that poor management was the main reason the mine’s underground expansion has run into problems affecting its cost and timeline.
While Rio has said it understands stakeholders’ frustration it believes the review did not sufficiently recognize the full impact of weaker than expected rock conditions, which forced the mining giant to redesign the project.
Costs to expand the Oyu Tolgoi mine, Rio’s biggest copper growth project, have ballooned up to $6.75 billion from Rio’s original budget of $5.3 billion set in 2016, and this led to friction over funding with mine operator Turquoise Hill (TSX, NYSE: TRQ). The firms finally reached an agreement in April.
Canada’s Turquoise Hill, in which Rio has a 50.8% stake, owns 66% of Oyu Tolgoi. The rest is held by the Mongolian government.
“We are concerned that the report takes a narrow view of what constitutes geotechnical impacts on the project,” Rio’s head of projects Mark Davies said in a letter to Mongolia’s justice minister Khishgee Nyambaatar, quoted by the Financial Times.
The message, sent last week, said other issues, such as fitting out a key access shaft, had also affected the project. It added those matters were “transparently reported” to its partners.
Davies said the fact that 96% of the workforce was Mongolian, which is “far higher” than initially planned also weighed on the project.
“The investment in the national workforce did have an impact on project costs and schedule; more than the ICG recognizes,” the letter said.
Rio Tinto has repeatedly said the underground expansion of Oyu Tolgoi is its most important growth project. First production, initially scheduled for late 2020, is now expected in October 2022.
Once completed, the mine’s underground section will lift production from 125,000–150,000 tonnes in 2019 to 560,000 tonnes at peak output, which is now expected by 2025 at the earliest. This would make it the biggest new copper mine to come on stream in several years.
Short Link:
https://www.miningnews.ir/En/News/616729
Copper traded near $10,000 a ton, hitting a new two-year high on its way, as investors continue to pile in on a bet that ...
Adriatic Metals is taking over as the operator of the Rupice deposit development, which is part of the company’s Vares ...
A prefeasibility study for Predictive Discovery’s (ASX: PDI) Bankan gold project in Guinea gives it a net present value ...
A Native American group has asked all members of a US appeals court on Monday to overturn an earlier ruling that granted ...
Codelco is exploring more partnerships with the private sector as Chile’s state copper behemoth looks to recover from a ...
The London Metal Exchange (LME) on Saturday banned from its system Russian metal produced on or after April 13 to comply ...
Iron ore futures prices drifted higher on Thursday as the latest soft data from top consumer China triggered renewed ...
Peru’s Las Bambas copper mine, owned by China’s MMG, is facing renewed blockades of a key transport route after failed ...
Vitol Group confirmed that it’s starting to rebuild a trading book for metals after a long stint out of the market, with ...
No comments have been posted yet ...