Mining News Pro - An independent review has been completed on the feasibility study for the Egoli project at gold miner Pan African’s Evander mine, in Mpumalanga.
First gold is now expected to be produced about 20 months after construction starts, with ramp-up to steady state production to be achieved 16 months after that.
The low-cost brownfield project, which will capitalise on the Evander mine’s existing established infrastructure during its development and exploitation, has an initial life-of-mine (LoM) of nine years, with yearly gold production estimated at an average of 72 000 kg at an average head grade of 6.61 g/t.
Average LoM gold production is estimated at 17 771 kg, or about 570 000 oz.
Additional geological and operational upside exists when the inferred resources are accessed as underground development proceeds, which will potentially increase the LoM to 14 years.
In a report published on July 30, Pan African says the study “demonstrates a compelling organic growth project” with peak funding set at just over R1-billion with a capital payback period of 3.8 years from project inception.
All-in sustaining costs range at R399 600/kg, or $777/oz.
Detailed project scheduling and planning is in progress and is expected to be completed in the first quarter of 2021, while funding is expected to be finalised in the second quarter of 2021.
Inception of the Egoli project is scheduled to start in the second quarter of the 2021 financial year, with the dewatering of the decline followed by re-quipping, standard footwall development and further deepening of the decline and on-reef development.
The project also has a strong environmental social and governance credentials, as it is already fully licenced and empowered, the closure cost rehabilitation liability is fully funded and the company intends to utilise the existing tailings storage facility at Evander for the project, resulting in there being no additional environmental footprint.
The Evander solar plant, which will be completed in the next year, is expected to also contribute to cost savings and reduced emissions at Evander’s operations
Short Link:
https://www.miningnews.ir/En/News/575733
Private credit managers are doing significantly more fossil-fuel deals now than just a few years ago, as they step into ...
Several people have been killed in Liberia in an accident at an abandoned gold mine, the West African country’s mines ...
Canada’s corporate ethics watchdog on Tuesday said it was likely that human rights abuses had occurred at a mine in ...
Commodities usually rally when central banks cut interest rates, bolstering the case for going long raw materials in the ...
Iron ore futures edged higher on Monday, supported by hopes of further recovery in demand in top consumer China and ...
Awalé Resources (TSXV: ARIC) stock soared on Monday after the Newmont-backed gold explorer reported outstanding assay ...
Iron ore futures tumbled in Singapore, extending a stretch of volatile trading amid deepening anxiety over Chinese ...
French President Emmanuel Macron said on Monday the government is seeking to designate new regulated gold mining zones ...
Newmont Corp. has kicked off the sale of its Akyem gold mine in Ghana, which is attracting interest from potential ...
No comments have been posted yet ...