Gem and Diamond

Alrosa considers going underground at Jubilee

Alrosa considers going underground at Jubilee
Mining News Pro - Russian miner Alrosa’s investment committee has approved financing for preliminary engineering studies at the Jubilee diamond mine, to provide up-to-date information to decide on the construction of an underground mine.
  Zoom:

According to Mining News Pro - The Jubilee pipe of the Aikhal division is currently being mined by openpit methods.

In 2019, the company considered technical specifications and decided to start preliminary works to set the stage for design and engineering of the prospective underground mine to extract reserves from deeper horizons of the pipe (from -100 m to -680 m levels).

The approved complex of studies include preparation of engineering surveys and feasibility studies for the underground mine and infrastructure. The financing for this phase is budgeted at around ₽63-million.

At a pit depth of 480 m, Jubilee has a mining capacity of 5.2-million tonnes a year.

According to the current production plan, it will operate until 2034 with a pit deepening to 720 m (corresponds to -100 m mark).

The company expects to get the feasibility study for the Jubilee underground mine construction, as well as updated resources and reserves in 2022.

A final decision on the project implementation will base on these documents.


   Short Link:  
Related News
Esfahan Mobarakeh Steel co.
HOSCO
khuzestan steel
chadormalu Co.
ghadir neiriz co
IranAluminaJaajarm
sangan steel
ahan o fulad golgohar