Mining News Pro - Equinox Gold reports that the new primary jaw crusher at its Aurizona Gold Mine in Brazil has been energised and dry tested with the expectation of putting first ore through the system in early January 2019.
According to Mining News Pro - The ROM ore is trucked from the open pits and dumped directly into the ROM surge bin with 700 mm spacing bars, or stockpiled on the ROM storage pad and then reclaimed by a FEL to the surge bin. Any ore coarser than 700 mm is broken down by a mobile breaker. The ore in the surge bin is reclaimed by the 1,500 mm wide by 9 m long apron feeder. The ROM ore is fed onto the vibrating grizzly feeder, where the screen oversize coarser than 115 mm is directed to the jaw crusher, which crushes the screen oversize to a P80 of approximately 150 mm. The crushed ore reports to the surge bin feed conveyor which also receives the vibrating screen undersize. The combined crushed ore and the screen undersize will be conveyed to the SAG mill feed surge bin.
Project update summary:
Crusher circuit including vibrating feeder has been energised and dry tested
Commissioning team ramping up and training programs are underway
Engineering and procurement activities are complete
Tailings storage facility is complete
Powerline sub-station upgrades are complete and awaiting final verification by the state utility
Ancillary buildings and facilities are complete
At the end of November, processing plant construction was 90% complete
Concrete work is complete
Structural steel erection is 96% complete
Equipment and plate work installation is 86% complete
Piping is 76% complete
Electrical and instrumentation is 50% complete
Pre-production mining is nearing completion
More than 6.4 Mt of material moved
730,000 t of ore stockpiled and ready for commissioning
The construction team is focused on piping, electrical and instrumentation. The main transmission line is ready to provide full energization to all equipment, and site-wide distribution circuits to local electrical rooms are being commissioned to enable testing of individual equipment components.
Equinox Gold commenced full-scale construction at Aurizona in January 2018 and pre-production mining in April 2018. Approximately $116 million was spent at the end of November 30, 2018, including fiscal 2017 spending related to construction activities. The project remains fully funded. In addition to existing cash reserves, the company has $10 million remaining to draw against its $85 million construction credit facility.
Short Link:
https://www.miningnews.ir/En/News/319215
Canada’s corporate ethics watchdog on Tuesday said it was likely that human rights abuses had occurred at a mine in ...
Commodities usually rally when central banks cut interest rates, bolstering the case for going long raw materials in the ...
Awalé Resources (TSXV: ARIC) stock soared on Monday after the Newmont-backed gold explorer reported outstanding assay ...
French President Emmanuel Macron said on Monday the government is seeking to designate new regulated gold mining zones ...
Newmont Corp. has kicked off the sale of its Akyem gold mine in Ghana, which is attracting interest from potential ...
Vista Gold has released an updated feasibility study for its Mt Todd gold project in Northern Territory, Australia, to ...
Gold production in Burkina Faso declined last year as deteriorating security conditions in the West African nation ...
Gold snapped nine days of record-breaking gains as underlying US inflation topped forecasts for a second month in ...
A Senegalese opposition coalition backed by popular firebrand Ousmane Sonko launched its presidential campaign platform ...
No comments have been posted yet ...