Mining News Pro - OZ Minerals has pushed back the planned delivery of first concentrate at its Carrapateena copper-gold project in South Australia by a month.
According to Mining News Pro - The company has postponed the milestone from November to December this year due to incorrect items being supplied for the minerals processing plant.
OZ Minerals will revise its 2020 production guidance for Carrapateena. It was initially targeted at 2000–4000 tonnes of copper and 3000–6000 ounces of gold.
The company expects to provide the new guidance for 2020 along with the release of its December quarter production report in late January.
OZ Minerals chief executive Andrew Cole was disappointed by the weeks-long postponement considering the remainder of Carrapateena’s construction was either complete or nearing completion.
The delay, however, will not influence Carrapateena’s project ramp up in 2020 given the advanced state of the underground development, according to Cole.
“Over 200,000 tonnes of ore is now stockpiled in preparation for commissioning of the minerals processing plant and underground development and installation of underground infrastructure is progressing well,” Cole said.
There is also no significant cash impact from the first delivery’s postponement, with 2019 growth capital expenditure for Carrapateena remaining at $540–$570 million. It will, however, put Carrapateena’s project development cost at $950–$980 million.
The news coincides with an update to Carrapateena’s ore reserve, with the site’s copper metal tonnes increasing by around 7 per cent after sub-level cave mining.
Carrapateena copper metal mineral resource has increased by around 34 per cent to 5.2 million tonnes, and gold metal has risen by around 29 per cent to 7.4 ounces.
“It is pleasing to see such substantial growth in the Carrapateena mineral resources as we progress our expansion studies in the province,” Cole said.
“This further demonstrates the potential for Carrapateena to extract significantly more value through an expansion beyond the sub-level cave.”
OZ Minerals has also extended its Prominent Hill mine life by another year to 2031, which is propped up by around 80 million tonnes of mineral resource outside the mine plan.
Short Link:
https://www.miningnews.ir/En/News/444437
AbraSilver Resource said on Monday it has received investments from both Kinross Gold and Central Puerto, Argentina’s ...
Gold took a tumble as haven demand waned after geopolitical tensions eased in the Middle East.
Copper traded near $10,000 a ton, hitting a new two-year high on its way, as investors continue to pile in on a bet that ...
The four largest indigenous communities in Chile’s Atacama salt flat suspended dialogue with state-run copper giant ...
A prefeasibility study for Predictive Discovery’s (ASX: PDI) Bankan gold project in Guinea gives it a net present value ...
A Native American group has asked all members of a US appeals court on Monday to overturn an earlier ruling that granted ...
Codelco is exploring more partnerships with the private sector as Chile’s state copper behemoth looks to recover from a ...
Representatives from the Peñas Negras Indigenous community, in northwestern Argentina, clashed with heavily armed police ...
The London Metal Exchange (LME) on Saturday banned from its system Russian metal produced on or after April 13 to comply ...
No comments have been posted yet ...