Vale to move forward with Serra Sul iron ore expansion
Saturday, August 15, 2020 - 12:42:40 PM
Mining

The $1.5 billion Serra Sul 120 project aims to increase the S11D mine-plant capacity by 20 million tonnes to 120 million tonnes of iron ore a year. Once completed, it will increase output at Vale’s North System to 260 million tonnes a year.

The Rio de Janeiro-based mining giant said completion of Serra Sul 120 is expected in the first half of 2024.

The project includes the opening of new mining areas, the duplication of the long-distance belt conveyor (TCLD), which will require a $385 million investment. It also involves implementing new processing lines at the plant and expanding storage areas, Vale said.

Vale noted that bringing forward the multi-year project and the ongoing impact from the coronavirus pandemic means the company will have to revise guidance on investments for 2021 and the 2022-2024 period.

Accidents and pandemic
Vale is still reeling from a tailings dam collapse at one of its mines that killed 270 people last year.

The disaster forced the company to suspend operations and curtail production at several of its mines. The iron ore producer originally estimated it would take two to three years to reach the annual output target of 400 million tonnes it had originally set for 2019.

The coronavirus pandemic, however, has weighed further on Vale’s plans, with the company lowering its guidance for the year on more than one occasion.